<?xml version="1.0" encoding="UTF-8"?><ns2:project xmlns:ns1="http://gtr.rcuk.ac.uk/gtr/api" xmlns:ns2="http://gtr.rcuk.ac.uk/gtr/api/project" xmlns:ns3="http://gtr.rcuk.ac.uk/gtr/api/fund" xmlns:ns4="http://gtr.rcuk.ac.uk/gtr/api/person" xmlns:ns5="http://gtr.rcuk.ac.uk/gtr/api/project/outcome" xmlns:ns6="http://gtr.rcuk.ac.uk/gtr/api/organisation" ns1:created="2026-06-03T15:52:43Z" ns1:href="http://gtr.ukri.org/gtr/api/projects/489CF8DC-9D72-4CE0-A034-50B8E9349AB4" ns1:id="489CF8DC-9D72-4CE0-A034-50B8E9349AB4"><ns1:links><ns1:link ns1:href="http://gtr.ukri.org/gtr/api/persons/85908E5F-2DD7-4E49-AC83-89B9BC12D18A" ns1:rel="PM_PER"/><ns1:link ns1:href="http://gtr.ukri.org/gtr/api/organisations/40BE0C0C-E92B-4EFE-9514-9AABAC4DA91C" ns1:rel="LEAD_ORG"/><ns1:link ns1:href="http://gtr.ukri.org/gtr/api/organisations/40BE0C0C-E92B-4EFE-9514-9AABAC4DA91C" ns1:rel="PARTICIPANT_ORG"/><ns1:link ns1:end="2021-12-31T00:00:00Z" ns1:href="http://gtr.ukri.org/gtr/api/funds/1289B282-62FB-46D2-B9B5-355A1FCE08EF" ns1:rel="FUND" ns1:start="2021-01-01T00:00:00Z"/></ns1:links><ns2:identifiers><ns2:identifier ns2:type="RCUK">98359</ns2:identifier></ns2:identifiers><ns2:title>Automation in Survey Data Procession for Structure Gauging Phase 2</ns2:title><ns2:status>Closed</ns2:status><ns2:grantCategory>Small Business Research Initiative</ns2:grantCategory><ns2:leadFunder>Innovate UK</ns2:leadFunder><ns2:abstractText>This project change request is being raised to agree a change to the delivery dates for milestones 2 and 3. 

The original milestone dates as agreed in the contract were: 

Milestone 1 - Stage 2 core system development - 01/05/21 
Milestone 2 - Stage 3 field testing and validation - 01/07/21
Milestone 3 - Stage 4 Final project, exploitation plan, project close out meeting and demonstration 1/08/21

The following revised delivery dates are requested:

Milestone 1 - complete no change
Milestone 2 - not fully completed revised date 01/09/21
Milestone 3 - revised date 31/10/21</ns2:abstractText></ns2:project>