Automation in Survey Data Procession for Structure Gauging Phase 2
Lead Participant:
ATKINS LIMITED
Abstract
This project change request is being raised to agree a change to the delivery dates for milestones 2 and 3.
The original milestone dates as agreed in the contract were:
Milestone 1 - Stage 2 core system development - 01/05/21
Milestone 2 - Stage 3 field testing and validation - 01/07/21
Milestone 3 - Stage 4 Final project, exploitation plan, project close out meeting and demonstration 1/08/21
The following revised delivery dates are requested:
Milestone 1 - complete no change
Milestone 2 - not fully completed revised date 01/09/21
Milestone 3 - revised date 31/10/21
The original milestone dates as agreed in the contract were:
Milestone 1 - Stage 2 core system development - 01/05/21
Milestone 2 - Stage 3 field testing and validation - 01/07/21
Milestone 3 - Stage 4 Final project, exploitation plan, project close out meeting and demonstration 1/08/21
The following revised delivery dates are requested:
Milestone 1 - complete no change
Milestone 2 - not fully completed revised date 01/09/21
Milestone 3 - revised date 31/10/21
Lead Participant | Project Cost | Grant Offer |
---|---|---|
ATKINS LIMITED | £217,375 | £ 217,375 |
  | ||
Participant |
||
INNOVATE UK |
People |
ORCID iD |
Shane McNamara (Project Manager) |