Nuclear Fission Reactor Thermal-Hydraulics (NUFRETH) - UKAEA
Lead Research Organisation:
United Kingdom Atomic Energy Authority
Department Name: Culham Centre for Fusion Energy
Abstract
Abstracts are not currently available in GtR for all funded research. This is normally because the abstract was not required at the time of proposal submission, but may be because it included sensitive information such as personal details.
People |
ORCID iD |
| Christopher Harrington (Principal Investigator) |
| Description | The Nuclear Fission Reactor Thermal-Hydraulics (NUFRETH) grant sought to establish a testing facility for large-scale, high pressure and high temperature (15.5 MPa, 345 °C) nuclear thermal hydraulics and heat transfer in water-cooled components with high resolution diagnostics. The project was funded through the EPSRC's National Nuclear User (NNUF) programme and commenced in October 2021. The facility is intended to be strategically key in offering capabilities to both the fission and fusion communities to enhance knowledge transfer through an open-access facility for academia and industry. Early in the project, challenges to the delivery of the planned capability within the grant timescales and budget were encountered that required a change in scope. In particular, significant inflation and extended component lead times were encountered, caused by labour shortages and the release of pent-up demand after the COVID pandemic, alongside a lack of availability of raw materials due to the conflict in eastern Europe and supply issues from China. As a result, the scope of work was reduced, in agreement with EPSRC, to cover the Concept Design, Interim Preliminary Design and selected de-risking activities for the proposed future facility. No capital purchasing was undertaken as a deliberate decision to avoid redundant spend on components that would yield only a partial system. As a result of these challenges, the grant has delivered the following outcomes that have advanced the design of the facility: • Facility Use Case and Requirements Documentation: Definition of system operating parameters and phenomena of interest for range of users as outlined in original grant proposal. Formalisation of stakeholder and system requirements to meet desired use cases. • Concept Design: Initial concept design of system, including primary flow loop functional basis, system layout, and hazard identification. • Interim Preliminary Design: Matured system design to increase confidence in achieving system requirements, including design description, general arrangement drawings, flow sheets, concept of operations, preliminary component identification, and safety analysis. • Equipment Specifications: Draft equipment specifications for long lead-time items, including main circulation pump and system Initial Test Unit. • Future Engineering Timeline and System Cost Evaluation: Definition of the remaining engineering phases, with timeline estimations, and detailed cost breakdown for remaining resource and equipment spend required to reach full facility realisation. These deliverables will be invaluable in taking forward the facility to full realisation through other funding mechanisms. Within the facility design, a number of technical challenges not envisaged at the initial proposal stage have been identified. While solutions for these are present within the current design, additional complexity and equipment cost are the resultant trade-off. Therefore, in order to maintain a reasonable balance against the facility research goals, a further set of outcomes of the grant are a number of recommendations for rationalisation in future stages of the facility realisation. This includes: • Identification of potential system modifications and trade-off with use cases that would enable lower complexity, lower cost solutions to be found. • Concept design of a "Demonstration Test Unit" for utilisation on smaller existing facilities at UKAEA to act as a de-risking precursor for some of the key diagnostic systems. • Compilation of a Lessons Learnt Register to enable knowledge transfer of technical and project risks and issues to the future delivery team. |
| Exploitation Route | The project has been extensively documented and brought to a controlled close that allows the further development of the envisaged facility to be pursued at a later date, eventually leading to its full realisation. The key steps leading to this outcome will be: • System Design Review and Optimisation: Review of changes to the research landscape in the interim period since the original proposal and identification of relevant potential system modifications to reduce cost and complexity. • Detailed Design: Finalisation of the system design to a point sufficient to enable procurement of all equipment and installation on site. • Facility Manufacture & Build: Procurement, manufacture, delivery, and installation of system on-site. • Commissioning & Acceptance: Commissioning of system and handover to operations. The requirements for these steps have been captured within the existing project outcomes, including detailed breakdowns of timeline and cost estimations. Additional intermediate steps to take forward the outcomes of the completed work without requiring build of the full system are possible through the development of the "Demonstration Test Unit", which would provide a lower cost de-risking of key diagnostic techniques alongside achievement of a valuable subset of the original research goals. |
| Sectors | Energy |
| Title | Experimental Flow Boiling Facility Interim Preliminary Design |
| Description | The outcomes of the grant include the comprehensive document set to define the Interim Preliminary Design of the facility. This entails: - Basis Of Design - Requirements Cross Verification Matrix - Interim Preliminary Design Description Document - ANNA Process Flow Diagram - Initial Test Unit Equipment Specification - Main Circulating Pump Equipment Specification - AVEVA Simulation Results - Load Schedule - Single Line Diagram (SLD) - Visio Layout - Lifecycle Cost Estimate - Mass & Energy Balance Calculations and Results - 3D CAD Model - General Arrangement Drawing - HAZID and HAZID Briefing Note - Interim Preliminary Design Review Presentation - Waste and Maintenance Philosophy - FEED Recommendations Document |
| Type Of Technology | Systems, Materials & Instrumental Engineering |
| Year Produced | 2023 |
| Impact | The design has enabled discussion of future funding routes to realise the facility with potential collaborators and greater engagement with the thermal hydraulic research community. The completion of the design itself led to new understanding of the challenges and opportunities associated with such a facility, enabling continuous re-evaluation of the research landscape. |
| Description | Participation in the Collaborative Computational Project in Nuclear Thermal Hydraulics (CCP-NTH) |
| Form Of Engagement Activity | Participation in an activity, workshop or similar |
| Part Of Official Scheme? | No |
| Geographic Reach | National |
| Primary Audience | Professional Practitioners |
| Results and Impact | Attendance at annual meetings of the Collaborative Computational Project in Nuclear Thermal Hydraulics (CCP-NTH), including providing updates to audience on NUFRETH proposal developments and developing research aims beyond the grant. |
| Year(s) Of Engagement Activity | 2021,2022,2023,2024 |