Optimisation of network outage schedules
Lead Research Organisation:
University of Strathclyde
Department Name: Inst for Energy and Environment
Abstract
The long-term reliability of an electric power system and continuity of supply of power to consumers are critically dependent on the timely maintenance of system assets and the construction of new assets. New assets are installed in extension of the system to provide greater power transfer capability or in replacement of old equipment that has reached the end of its economic or technical life, i.e. where the probability of an irreparable failure is excessively high or repair or maintenance would be uneconomic. Both maintenance and construction work require the removal of parts of the system from service so that the relevant parts of it can be safely accessed and worked on. However, the remainder of the system must be capable of meeting minimum service standards, i.e. be capable of meeting demand without overloading of the remaining network branches, violation of voltage limits or risk of instability of the system.As electric power transmission and distribution networks in the UK age, in the next 1 to 10 years, very large parts of them will need to be replaced. The associated construction outages will be very much longer than maintenance outages; due to the 'bow wave' of asset replacements needed, the number of outages to be taken will be higher than ever before. This will occur at the same time as, following year-on-year demand growth, changes to generation patterns and greater restrictions on network owners' ability to add new circuit routes, systems are utilised to a greater degree than ever before. Moreover, still more construction outages are needed for the accommodation of new generation, in particular renewables.In order to ensure that a sufficient number of network outages of adequate length can be taken by the times at which they are required while maintaining system security, a huge effort must be expended optimising the schedule of outages. This requires detailed analysis of system security under different outage conditions and appropriate management of the risks of dependencies on availability and prices of generation, fluctuations in demand and overrun of work on the outaged network assets. The worst outcome of a failure to manage the risks would be that critical outages cannot be taken with the result that essential network assets are at greater risk of failure and that new generation / in particular renewables / cannot be accommodated.This project aims to develop methods to facilitate the meeting of the greater-than-ever challenges in the scheduling of network outages and demonstrate them by means of prototype software tools. The result will be reduction of the aforementioned risks and a more efficient and timely facilitation of the connection of renewable generation.
Publications
Bell K
(2012)
The Need for Interconnection Reserve in a System With Wind Generation
in IEEE Transactions on Sustainable Energy
Jianing Cao (Co-Author)
(2010)
Generation maintenance scheduling in a liberalised electricity market
K Bell
(2010)
45th Universities' Power Engineering Conference
K Bell
(2006)
IEE Power Engineer
K Bell
(2010)
CIGRE Session
Mohamed Shaaban (Co-Author)
(2009)
Assessment of tradable short-term transmission access rights to integrate renewable generation
Description | CIGRE WG C1.24 on "Tools for developing Optimum Transmission Development Plans" |
Organisation | International Council on Large Electric Systems (CIGRE) |
Country | France |
Sector | Charity/Non Profit |
PI Contribution | Member : Contribution to the work of national or international committees and working groups : This working group will study the need for new tools and techniques to assist in the development and economic justification of long-term transmission plans. This will be achieved by: (1) reviewing previous CIGRE studies to identify and build on relevant material; (2) conducting a survey to establish international practice and identify the strengths and deficiencies of existing tools; (3) reviewing survey responses and available literature to identify the current state of the art in this area and recommend areas for future development. |
Start Year | 2009 |
Description | CIGRE WG C1.24 on "Tools for developing Optimum Transmission Development Plans" |
Form Of Engagement Activity | A formal working group, expert panel or dialogue |
Part Of Official Scheme? | No |
Primary Audience | |
Results and Impact | Member : Contribution to the work of national or international committees and working groups : This working group will study the need for new tools and techniques to assist in the development and economic justification of long-term transmission plans. . |
Year(s) Of Engagement Activity | 2009 |
Description | CIGRE WG C1.24 on Tools for developing Optimum Transmission Development Plans |
Form Of Engagement Activity | A formal working group, expert panel or dialogue |
Part Of Official Scheme? | No |
Geographic Reach | International |
Primary Audience | |
Results and Impact | Member : Contribution to the work of national or international committees and working groups : This working group will study the need for new tools and techniques to assist in the development and economic justification of long-term transmission plans. This will be achieved by: (1) reviewing previous CIGRE studies to identify and build on relevant material; (2) conducting a survey to establish international practice and identify the strengths and deficiencies of existing tools; (3) reviewing survey responses and available literature to identify the current state of the art in this area and recommend areas for future development. |
Year(s) Of Engagement Activity | 2009 |